QUESTION ON CONDUCT PROCUREMENT’S

PMP Certification,Project Management
Q: Which of the following is NOT a tool used in the “conduct procurements” process? A. Bidders Conference B. Independent Estimates C. Procurement Negotiation D. Contract Types Correct Option: D EXPLANATION Contract types is a tool used in the "plan procurements" process Please let me know why B is not the correct Answer.