A project manager has some new members join in her team. She wants to help them see their roles and provide the project team with an understanding of where their work packages fit in the project management plan. Which of the following would be the most suitable document?

PMP Certification,Project Management
What the correct answer for the question above?
  • Requirements documentation
  • Requirements traceability matrix
  • Responsibility assignment matrix
  • Work breakdown structure