QUESTION ON CONDUCT PROCUREMENT’S

PMP Certification,Project Management
Q: Which of the following is NOT a tool used in the “conduct procurements” process? A. Bidders Conference B. Independent Estimates C. Procurement Negotiation D. Contract Types Correct Option: D EXPLANATION Contract types is a tool used in the "plan procurements" process Please let me know why B is not the correct Answer.
  • 0

    replies

  • 436

    views

  • 0

    users

8 years

For comments Post Please Login

Suggested Topics

Topic Category Users Replies Views Activity
PMP Certification,Project Management 0 0 3684 No Activity
PMP Certification,Project Management 0 0 3657 No Activity
PMP Certification,Project Management 0 0 3670 No Activity
PMP Certification,Project Management 0 0 3682 No Activity
PMP Certification,Project Management 0 0 3642 No Activity